Project description
This project involved the construction of glass recycling facilities at numerous transfer stations with the Corangamite Shire. The locations included Timboon, Port Campbell, Naroghid, Derrinallum, Simpson and Lismore.
While each project was similar the designs, conditions of site and the detail of works changed for each location. Some sites required a concrete slab only, others required entrance slabs and then there was repairing block retaining walls or building new block retaining walls.
Features:
Project duration: eight months